  "2026-03-11|Roosevelt School Presentation and School Plan for Student Achievement (SPSA) Approval": {
    "roosevelt": {
      "en": "Annual school presentation to the Board; SPSA review",
      "es": "Presentación escolar anual ante la Mesa Directiva; SPSA"
    }
  },
  "2026-03-11|McKinley Institute of Tech School Presentation and School Plan for Student Achievement (SPSA) Approval": {
    "mckinley-mit": {
      "en": "Annual school presentation to the Board; SPSA review",
      "es": "Presentación escolar anual ante la Mesa Directiva; SPSA"
    }
  },
  "2026-03-11|Hoover School Presentation and School Plan for Student Achievement (SPSA) Approval": {
    "hoover": {
      "en": "Annual school presentation to the Board; SPSA review",
      "es": "Presentación escolar anual ante la Mesa Directiva; SPSA"
    }
  },
  "2026-03-11|Approval of the Addendum to the Measure U Application for Roosevelt Elementary School for the 2025-2026 School Year": {
    "roosevelt": {
      "en": "Measure U addendum for 2025-26 school year",
      "es": "Addenda de Medida U para el año escolar 2025-26"
    }
  },
  "2026-03-11|Approval of the Addendum to the Measure U Application for McKinley Middle School for the 2025-2026 School Year": {
    "mckinley-mit": {
      "en": "Measure U addendum for 2025-26 school year",
      "es": "Addenda de Medida U para el año escolar 2025-26"
    }
  },
  "2026-03-11|Approval of the Addendum to the Measure U Application for Hoover Community School for the 2025-2026 School Year": {
    "hoover": {
      "en": "Measure U addendum for 2025-26 school year",
      "es": "Addenda de Medida U para el año escolar 2025-26"
    }
  },
  "2026-03-11|Approval of Roy Cloud Field Trip to Marine Science Institute – March 25, 2026": {
    "roy-cloud": {
      "en": "Field trip to Marine Science Institute",
      "es": "Excursión al Instituto de Ciencias Marinas"
    }
  },
  "2026-03-11|Approval of North Star Academy Field Trip to Pinnacles National Park – May 19 – May 22, 2026": {
    "north-star": {
      "en": "Field trip to Pinnacles National Park",
      "es": "Excursión al Parque Nacional Pinnacles"
    }
  },
  "2026-02-11|Personnel Changes: 2 new Crossing Guard positions — McKinley School + North Star Schools (3 hrs each, ~$13K/yr each)": {
    "mckinley-mit": {
      "en": "New crossing guard position (~$13K/yr)",
      "es": "Nueva posición de guardia de cruce (~$13K/año)"
    },
    "north-star": {
      "en": "New crossing guard position (~$13K/yr)",
      "es": "Nueva posición de guardia de cruce (~$13K/año)"
    }
  },
  "2026-02-04|Revised Measure S Implementation Plan (Partial) — refines districtwide projects: TK/K classroom projects at Clifford, Henry Ford, and Roy Cloud; utility upgrades (aging water/sewer/gas/storm); kitchen upgrades (code compliance, scratch-prepared meals); elevator replacements (ADA/Title 24); HVAC phasing. Partial approval preserves Board flexibility as enrollment trends and funding evolve.": {
    "clifford": {
      "en": "Measure S plan updated; TK/K classroom project included",
      "es": "Plan de Medida S actualizado; proyecto de aulas TK/K incluido"
    },
    "henry-ford": {
      "en": "Measure S plan updated; TK/K classroom project included",
      "es": "Plan de Medida S actualizado; proyecto de aulas TK/K incluido"
    },
    "roy-cloud": {
      "en": "Measure S plan updated; TK/K classroom project included",
      "es": "Plan de Medida S actualizado; proyecto de aulas TK/K incluido"
    }
  },
  "2026-02-04|Resolution No. 16: Lease-Leaseback with Blach Construction for HVAC Phase 2 at Clifford, Orion, Kennedy Middle School. Preconstruction $29,595 + early procurement authorization up to $3M, total NTE $3,029,595 from Measure S Bond. Construction scheduled Summer 2026. 4 proposals received Jan 21, 2026; Blach selected on best value (lowest cost, lowest overhead/profit at 2.75%). — 7 attachments": {
    "clifford": {
      "en": "HVAC Phase 2 contract; construction scheduled Summer 2026",
      "es": "Contrato de Fase 2 de HVAC; construcción programada para verano 2026"
    },
    "kennedy": {
      "en": "HVAC Phase 2 contract; construction scheduled Summer 2026",
      "es": "Contrato de Fase 2 de HVAC; construcción programada para verano 2026"
    },
    "orion": {
      "en": "HVAC Phase 2 contract; construction scheduled Summer 2026",
      "es": "Contrato de Fase 2 de HVAC; construcción programada para verano 2026"
    }
  },
  "2026-02-04|Solar Phase 2 Change Order #3: Kennedy MS #2 with Holt Renewables ($28,723.50 overtime allowance for DSA schedule impacts, NEM 2 deadline)": {
    "kennedy": {
      "en": "Solar Phase 2 change order ($28,724 overtime allowance)",
      "es": "Orden de cambio de Fase 2 solar ($28,724 de tiempo extra)"
    }
  },
  "2026-02-04|Solar Phase 2 Change Order #4: Roy Cloud with Holt Renewables ($86,170.50 overtime allowance, same DSA/NEM 2 reason)": {
    "roy-cloud": {
      "en": "Solar Phase 2 change order ($86,171 overtime allowance)",
      "es": "Orden de cambio de Fase 2 solar ($86,171 de tiempo extra)"
    }
  },
  "2026-02-04|Final Deductive Change Order for Blach HVAC Phase 1 — returning $2,293,889.47 to Measure S Bond Fund. Phase 1 (Taft, Hoover, Roosevelt, Adelante Selby + temp HVAC) substantially complete. Revised total contract: $17,447,987.53 (from original GMP $19,741,877).": {
    "adelante-selby": {
      "en": "HVAC Phase 1 complete; $2.3M returned to Measure S bond fund",
      "es": "Fase 1 de HVAC completada; $2.3M devueltos al fondo de bonos de Medida S"
    },
    "hoover": {
      "en": "HVAC Phase 1 complete; $2.3M returned to Measure S bond fund",
      "es": "Fase 1 de HVAC completada; $2.3M devueltos al fondo de bonos de Medida S"
    },
    "roosevelt": {
      "en": "HVAC Phase 1 complete; $2.3M returned to Measure S bond fund",
      "es": "Fase 1 de HVAC completada; $2.3M devueltos al fondo de bonos de Medida S"
    },
    "taft": {
      "en": "HVAC Phase 1 complete; $2.3M returned to Measure S bond fund",
      "es": "Fase 1 de HVAC completada; $2.3M devueltos al fondo de bonos de Medida S"
    }
  },
  "2026-02-04|Notice of Completion for Blach HVAC Phase 1 (5 separate notices: Temp Cooling, Taft, Roosevelt, Hoover, Adelante Selby) — 6 attachments": {
    "adelante-selby": {
      "en": "HVAC Phase 1 notice of completion filed",
      "es": "Aviso de finalización de Fase 1 de HVAC presentado"
    },
    "hoover": {
      "en": "HVAC Phase 1 notice of completion filed",
      "es": "Aviso de finalización de Fase 1 de HVAC presentado"
    },
    "roosevelt": {
      "en": "HVAC Phase 1 notice of completion filed",
      "es": "Aviso de finalización de Fase 1 de HVAC presentado"
    },
    "taft": {
      "en": "HVAC Phase 1 notice of completion filed",
      "es": "Aviso de finalización de Fase 1 de HVAC presentado"
    }
  },
  "2026-02-04|Kennedy Measure U Addendum ($252,653: $197,247 allotment + $55,406 carryover. Increases: clubs/activities $20K→$24.4K, music $7K→$12K, Chromebooks $20K→$48K, new $18K after-school tutoring)": {
    "kennedy": {
      "en": "Measure U addendum ($252,653); adds after-school tutoring, more Chromebooks",
      "es": "Addenda de Medida U ($252,653); añade tutoría extraescolar y más Chromebooks"
    }
  },
  "2026-02-04|Roy Cloud Measure U Addendum ($164,703: $158,880 + $5,823 carryover. Changes: cease Academic Counselor funding, reallocate to school supplies/tech $19.3K, tech repairs $5K, staff stipends $10K, substitute planning $5K)": {
    "roy-cloud": {
      "en": "Measure U addendum ($164,703); funds reallocated to supplies and tech",
      "es": "Addenda de Medida U ($164,703); fondos reasignados a materiales y tecnología"
    }
  },
  "2026-02-04|Comprehensive School Safety Plans (Public) for all 12 schools — 12 attachments (Taft, Roy Cloud, Roosevelt, Orion Alternative, North Star, McKinley, Kennedy, Hoover, Henry Ford, Garfield, Clifford, Adelante Selby)": {
    "adelante-selby": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    },
    "clifford": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    },
    "garfield": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    },
    "henry-ford": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    },
    "hoover": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    },
    "kennedy": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    },
    "mckinley-mit": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    },
    "north-star": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    },
    "orion": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    },
    "roosevelt": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    },
    "roy-cloud": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    },
    "taft": {
      "en": "Annual safety plan",
      "es": "Plan de seguridad anual"
    }
  },
  "2026-01-21|Atlas Pellizzari Electric EV Charger Installation ($70,520 at Adelante Selby, Clifford, Kennedy)": {
    "adelante-selby": {
      "en": "EV charger installation ($70,520 across three sites)",
      "es": "Instalación de cargadores de vehículos eléctricos ($70,520 en tres sitios)"
    },
    "clifford": {
      "en": "EV charger installation ($70,520 across three sites)",
      "es": "Instalación de cargadores de vehículos eléctricos ($70,520 en tres sitios)"
    },
    "kennedy": {
      "en": "EV charger installation ($70,520 across three sites)",
      "es": "Instalación de cargadores de vehículos eléctricos ($70,520 en tres sitios)"
    }
  },
  "2026-01-14|Measure U Addenda — Taft Community School ($126,135) and Clifford School ($253,304)": {
    "clifford": {
      "en": "Measure U addendum ($253,304)",
      "es": "Addenda de Medida U ($253,304)"
    },
    "taft": {
      "en": "Measure U addendum ($126,135)",
      "es": "Addenda de Medida U ($126,135)"
    }
  },
  "2026-01-14|Personnel Increase: 0.5 FTE Special Education Preschool Teacher ($90K/yr) at Garfield": {
    "garfield": {
      "en": "New 0.5 FTE Special Education Preschool Teacher position",
      "es": "Nueva posición de 0.5 FTE de maestra de preescolar de educación especial"
    }
  },
  "2025-12-17|Taft Measure U addendum ($126K for literacy coach, IB coordinator, college trips)": {
    "taft": {
      "en": "Measure U addendum ($126K); funds literacy coach and IB coordinator",
      "es": "Addenda de Medida U ($126K); financia entrenador de alfabetización y coordinador de IB"
    }
  },
  "2025-10-22|Garfield Measure U addendum — $79,463 allotment + $60,000 carryover = $139,463 total. $40K art teacher + $20K leveled readers": {
    "garfield": {
      "en": "Measure U addendum ($139,463); funds art teacher and leveled readers",
      "es": "Addenda de Medida U ($139,463); financia maestra de arte y libros nivelados"
    }
  },
  "2025-10-22|North Star 5th-grade Pier 40 field trip (San Francisco)": {
    "north-star": {
      "en": "5th-grade field trip to Pier 40 in San Francisco",
      "es": "Excursión de 5.° grado al Muelle 40 en San Francisco"
    }
  },
  "2025-10-22|Provisional Internship Permit — Kristin McGee-Morley, 6th grade, Kennedy": {
    "kennedy": {
      "en": "Provisional internship permit for 6th-grade teacher",
      "es": "Permiso de pasantía provisional para maestra de 6.° grado"
    }
  },
  "2025-10-08|Hoover Solar Phase II Change Order #4 (Holt Renewables) — PV Array #2 layout modification, $61,834.50 from Fund 40 (SFP)": {
    "hoover": {
      "en": "Solar Phase II change order ($61,835 for panel layout modification)",
      "es": "Orden de cambio de Fase II solar ($61,835 por modificación de distribución de paneles)"
    }
  },
  "2025-10-08|Orion 4th-grade Gold Rush field trip to Sierra Outdoor School (Sonora, CA), April 13-14, 2026": {
    "orion": {
      "en": "4th-grade Gold Rush field trip to Sierra Outdoor School",
      "es": "Excursión de 4.° grado sobre la Fiebre del Oro a la Escuela al Aire Libre de Sierra"
    }
  },
  "2025-10-08|SCCOE PBIS Tier 1/2 training agreement — 3 cohorts (Cohort 1: Adelante Selby/Garfield; Cohort 2: McKinley/Clifford/Orion; Cohort 3: Roosevelt/Kennedy/Henry Ford), $44,000 (LCAP)": {
    "adelante-selby": {
      "en": "PBIS Tier 1/2 staff training agreement",
      "es": "Acuerdo de capacitación del personal en PBIS Niveles 1/2"
    },
    "clifford": {
      "en": "PBIS Tier 1/2 staff training agreement",
      "es": "Acuerdo de capacitación del personal en PBIS Niveles 1/2"
    },
    "garfield": {
      "en": "PBIS Tier 1/2 staff training agreement",
      "es": "Acuerdo de capacitación del personal en PBIS Niveles 1/2"
    },
    "henry-ford": {
      "en": "PBIS Tier 1/2 staff training agreement",
      "es": "Acuerdo de capacitación del personal en PBIS Niveles 1/2"
    },
    "kennedy": {
      "en": "PBIS Tier 1/2 staff training agreement",
      "es": "Acuerdo de capacitación del personal en PBIS Niveles 1/2"
    },
    "mckinley-mit": {
      "en": "PBIS Tier 1/2 staff training agreement",
      "es": "Acuerdo de capacitación del personal en PBIS Niveles 1/2"
    },
    "orion": {
      "en": "PBIS Tier 1/2 staff training agreement",
      "es": "Acuerdo de capacitación del personal en PBIS Niveles 1/2"
    },
    "roosevelt": {
      "en": "PBIS Tier 1/2 staff training agreement",
      "es": "Acuerdo de capacitación del personal en PBIS Niveles 1/2"
    }
  },
  "2025-10-08|Caminar Amendment #1 — +$21,575 for Kennedy mental health counseling (amended total $89,971, funded by Kennedy donations)": {
    "kennedy": {
      "en": "Mental health counseling contract increased by $21,575",
      "es": "Contrato de consejería de salud mental aumentado en $21,575"
    }
  },
  "2025-09-18|College Advising Prep amendment — $80K increase to $240K total for Kennedy + McKinley math tutoring": {
    "kennedy": {
      "en": "Math tutoring contract increased to $240K total",
      "es": "Contrato de tutoría de matemáticas aumentado a $240K en total"
    },
    "mckinley-mit": {
      "en": "Math tutoring contract increased to $240K total",
      "es": "Contrato de tutoría de matemáticas aumentado a $240K en total"
    }
  },
  "2025-09-18|North Star Academy field trip to Marin Headlands": {
    "north-star": {
      "en": "Field trip to Marin Headlands",
      "es": "Excursión a Marin Headlands"
    }
  },
  "2025-09-18|Garfield Elementary Outdoor Ed Camp": {
    "garfield": {
      "en": "Outdoor education camp field trip",
      "es": "Excursión al campamento de educación al aire libre"
    }
  },
  "2025-09-10|QKA HVAC Design Services — $1,390,000 with Quattrocchi Kwok Architects for HVAC Phase 2 design at Kennedy, Orion, Clifford. Part of $22.25M total Phase 2 HVAC scope. Measure S Bond Fund.": {
    "clifford": {
      "en": "HVAC Phase 2 design services contract (Measure S)",
      "es": "Contrato de diseño de HVAC Fase 2 (Medida S)"
    },
    "kennedy": {
      "en": "HVAC Phase 2 design services contract (Measure S)",
      "es": "Contrato de diseño de HVAC Fase 2 (Medida S)"
    },
    "orion": {
      "en": "HVAC Phase 2 design services contract (Measure S)",
      "es": "Contrato de diseño de HVAC Fase 2 (Medida S)"
    }
  },
  "2025-08-27|Kennedy Middle School field trip to Yosemite": {
    "kennedy": {
      "en": "Field trip to Yosemite",
      "es": "Excursión a Yosemite"
    }
  },
  "2025-08-19|REACH Afterschool (City of Redwood City) — $1,184,298 for extended day learning at Adelante Selby, Henry Ford, Roosevelt, Orion (828 students total)": {
    "adelante-selby": {
      "en": "Afterschool extended learning program funded for 828 students",
      "es": "Programa de aprendizaje extendido después de clases financiado para 828 estudiantes"
    },
    "henry-ford": {
      "en": "Afterschool extended learning program funded for 828 students",
      "es": "Programa de aprendizaje extendido después de clases financiado para 828 estudiantes"
    },
    "orion": {
      "en": "Afterschool extended learning program funded for 828 students",
      "es": "Programa de aprendizaje extendido después de clases financiado para 828 estudiantes"
    },
    "roosevelt": {
      "en": "Afterschool extended learning program funded for 828 students",
      "es": "Programa de aprendizaje extendido después de clases financiado para 828 estudiantes"
    }
  },
  "2025-08-19|Catalyst Family Inc. Amendment — increased from 120 to 140 students, amended total $959,906 for North Star Academy afterschool": {
    "north-star": {
      "en": "Afterschool program expanded to 140 students",
      "es": "Programa después de clases ampliado a 140 estudiantes"
    }
  },
  "2025-08-19|YMCA of Silicon Valley — $200,000 afterschool at Adelante Selby (80 students)": {
    "adelante-selby": {
      "en": "YMCA afterschool program for 80 students",
      "es": "Programa después de clases de YMCA para 80 estudiantes"
    }
  },
  "2025-08-19|Roy Cloud field trip to GGNRA (6th grade science, Oct 1-3)": {
    "roy-cloud": {
      "en": "6th grade science field trip to GGNRA",
      "es": "Excursión de ciencias de 6.° grado al GGNRA"
    }
  },
  "2025-06-25|HVAC Phase II Approval — $21.25M for Kennedy Middle School, Orion Elementary, and Clifford Elementary. Applied Materials Engineering commissioning + Cypress Engineering inspection services.": {
    "clifford": {
      "en": "HVAC Phase 2 replacement project ($21.25M, Measure S)",
      "es": "Proyecto de reemplazo de HVAC Fase 2 ($21.25M, Medida S)"
    },
    "kennedy": {
      "en": "HVAC Phase 2 replacement project ($21.25M, Measure S)",
      "es": "Proyecto de reemplazo de HVAC Fase 2 ($21.25M, Medida S)"
    },
    "orion": {
      "en": "HVAC Phase 2 replacement project ($21.25M, Measure S)",
      "es": "Proyecto de reemplazo de HVAC Fase 2 ($21.25M, Medida S)"
    }
  },
  "2025-06-25|Catalyst Family Inc. — $838,599 afterschool services at North Star Academy": {
    "north-star": {
      "en": "Afterschool services contract",
      "es": "Contrato de servicios después de clases"
    }
  },
  "2025-06-11|Siemens Building Management System — HVAC controls at Adelante Selby, Hoover, Roosevelt, Taft. $1,878,600 from Measure S Bond Fund. Sole-source justification: Siemens is the only vendor certified for the existing BMS infrastructure.": {
    "adelante-selby": {
      "en": "HVAC building management system upgrade (Measure S)",
      "es": "Actualización del sistema de gestión de HVAC (Medida S)"
    },
    "hoover": {
      "en": "HVAC building management system upgrade (Measure S)",
      "es": "Actualización del sistema de gestión de HVAC (Medida S)"
    },
    "roosevelt": {
      "en": "HVAC building management system upgrade (Measure S)",
      "es": "Actualización del sistema de gestión de HVAC (Medida S)"
    },
    "taft": {
      "en": "HVAC building management system upgrade (Measure S)",
      "es": "Actualización del sistema de gestión de HVAC (Medida S)"
    }
  },
  "2025-06-11|Blach Construction GMP Amendment 1 for HVAC Phase 1 — $19,741,877 Guaranteed Maximum Price for lease-leaseback HVAC replacement at Adelante Selby, Hoover, Roosevelt, Taft + temporary cooling. Amends original preconstruction agreement. Measure S Bond Fund.": {
    "adelante-selby": {
      "en": "HVAC Phase 1 replacement construction contract (Measure S)",
      "es": "Contrato de construcción de reemplazo de HVAC Fase 1 (Medida S)"
    },
    "hoover": {
      "en": "HVAC Phase 1 replacement construction contract (Measure S)",
      "es": "Contrato de construcción de reemplazo de HVAC Fase 1 (Medida S)"
    },
    "roosevelt": {
      "en": "HVAC Phase 1 replacement construction contract (Measure S)",
      "es": "Contrato de construcción de reemplazo de HVAC Fase 1 (Medida S)"
    },
    "taft": {
      "en": "HVAC Phase 1 replacement construction contract (Measure S)",
      "es": "Contrato de construcción de reemplazo de HVAC Fase 1 (Medida S)"
    }
  },
  "2025-05-28|Approval of Kennedy's Field Trip Request to Italy, June 7, 2025, through June 16, 2025": {
    "kennedy": {
      "en": "International field trip to Italy",
      "es": "Excursión internacional a Italia"
    }
  },
  "2025-05-28|Approval of the School Plans for Student Achievement (SPSAs) for Hoover, McKinley, Kennedy, North Star Academy, and Roy Cloud": {
    "hoover": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    },
    "kennedy": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    },
    "mckinley-mit": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    },
    "north-star": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    },
    "roy-cloud": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    }
  },
  "2025-05-14|Approval of HVAC Replacement Project at Roy Cloud School Multi-use Building": {
    "roy-cloud": {
      "en": "HVAC replacement for multi-use building",
      "es": "Reemplazo de HVAC para el edificio de usos múltiples"
    }
  },
  "2025-05-14|Adoption of Resolution No. 24, Lease-Leaseback Agreement with Blach Construction for HVAC Projects at Adelante Selby School, Hoover School, Roosevelt School, and Taft School": {
    "adelante-selby": {
      "en": "Lease-leaseback construction agreement for HVAC project",
      "es": "Acuerdo de construcción de arrendamiento para proyecto de HVAC"
    },
    "hoover": {
      "en": "Lease-leaseback construction agreement for HVAC project",
      "es": "Acuerdo de construcción de arrendamiento para proyecto de HVAC"
    },
    "roosevelt": {
      "en": "Lease-leaseback construction agreement for HVAC project",
      "es": "Acuerdo de construcción de arrendamiento para proyecto de HVAC"
    },
    "taft": {
      "en": "Lease-leaseback construction agreement for HVAC project",
      "es": "Acuerdo de construcción de arrendamiento para proyecto de HVAC"
    }
  },
  "2025-05-14|Approval of Pilot of Benchmark 2022 English/Spanish Language Arts Curriculum at Taft and Garfield Elementary Schools for the 2025-2026 School Year": {
    "garfield": {
      "en": "New English/Spanish language arts curriculum pilot for 2025-26",
      "es": "Piloto de nuevo currículo de artes del lenguaje en inglés/español para 2025-26"
    },
    "taft": {
      "en": "New English/Spanish language arts curriculum pilot for 2025-26",
      "es": "Piloto de nuevo currículo de artes del lenguaje en inglés/español para 2025-26"
    }
  },
  "2025-05-14|Approval of the School Plans for Student Achievement (SPSAs) for Adelante Selby, Roosevelt, and Clifford": {
    "adelante-selby": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    },
    "clifford": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    },
    "roosevelt": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    }
  },
  "2025-05-14|Approval of Orion Growth Plan: A Sustainable Roadmap for Unity and Excellence": {
    "orion": {
      "en": "Multi-year school growth and improvement plan",
      "es": "Plan de crecimiento y mejora escolar a largo plazo"
    }
  },
  "2025-04-16|Approval of the School Plans for Student Achievement (SPSA) for Orion Alternative, Henry Ford, Taft, and Garfield Elementary Schools": {
    "garfield": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    },
    "henry-ford": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    },
    "orion": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    },
    "taft": {
      "en": "School Plan for Student Achievement (SPSA review)",
      "es": "Plan Escolar para el Logro Estudiantil (SPSA)"
    }
  },
  "2025-04-02|McKinley School Presentation for the 2024-2025 School Year": {
    "mckinley-mit": {
      "en": "Annual school presentation to the Board",
      "es": "Presentación escolar anual ante la Mesa Directiva"
    }
  },
  "2025-03-26|Clifford School Presentation for the 2024-2025 School Year": {
    "clifford": {
      "en": "Annual school presentation to the Board",
      "es": "Presentación escolar anual ante la Mesa Directiva"
    }
  },
  "2025-03-12|Henry Ford School Presentation for the 2024-2025 School Year": {
    "henry-ford": {
      "en": "Annual school presentation to the Board",
      "es": "Presentación escolar anual ante la Mesa Directiva"
    }
  },
  "2025-02-26|Approval of Addendum to the 2024-25 Measure U Application for Roy Cloud School": {
    "roy-cloud": {
      "en": "Measure U funding addendum",
      "es": "Adenda de financiamiento de la Medida U"
    }
  },
  "2025-02-26|Approval of Addendum to the 2024-25 Measure U Application for Orion Alternative and Mandarin Immersion School": {
    "orion": {
      "en": "Measure U funding addendum",
      "es": "Adenda de financiamiento de la Medida U"
    }
  },
  "2025-02-26|Approval of Addendum to the 2024-25 Measure U Application for North Star Academy (NSA)": {
    "north-star": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2025-02-05|Hoover and Roy Cloud School Presentations for the 2024-2025 School Year": {
    "hoover": {
      "en": "School presented its 2024-25 academic year report to the board.",
      "es": "La escuela presentó su informe del año escolar 2024-25 a la junta."
    },
    "roy-cloud": {
      "en": "School presented its 2024-25 academic year report to the board.",
      "es": "La escuela presentó su informe del año escolar 2024-25 a la junta."
    }
  },
  "2025-02-05|Approval of Addendum to 2024-25 Measure U Application for Hoover": {
    "hoover": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2025-02-05|Approval of Addendum to the 2024-25 Measure U Application for McKinley Institute of Technology (MIT)": {
    "mckinley-mit": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2025-02-05|Approval of Addendum to the 2024-25 Measure U Application for Kennedy Middle School": {
    "kennedy": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2025-01-15|Orion Alternative School Presentation for the 2024-2025 School Year": {
    "orion": {
      "en": "School presented its 2024-25 academic year report to the board.",
      "es": "La escuela presentó su informe del año escolar 2024-25 a la junta."
    }
  },
  "2025-01-08|Taft and Adelante Selby School Reports for the 2024-2025 School Year": {
    "adelante-selby": {
      "en": "School presented its 2024-25 academic year report to the board.",
      "es": "La escuela presentó su informe del año escolar 2024-25 a la junta."
    },
    "taft": {
      "en": "School presented its 2024-25 academic year report to the board.",
      "es": "La escuela presentó su informe del año escolar 2024-25 a la junta."
    }
  },
  "2025-01-08|Approval of Addendum to the 2024-25 Measure U Application for Clifford School": {
    "clifford": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2024-12-17|Approval of Addendum to the 2024-25 Measure U Application for Roosevelt School": {
    "roosevelt": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2024-12-11|Roosevelt Elementary School Presentation for the 2024-2025 School Year": {
    "roosevelt": {
      "en": "School presented its 2024-25 academic year report to the board.",
      "es": "La escuela presentó su informe del año escolar 2024-25 a la junta."
    }
  },
  "2024-12-11|Approval of Addendum to the 2024-25 Measure U Application for Henry Ford School": {
    "henry-ford": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2024-11-20|North Star Academy School Presentation for 2024-2025 School Year": {
    "north-star": {
      "en": "School presented its 2024-25 academic year report to the board.",
      "es": "La escuela presentó su informe del año escolar 2024-25 a la junta."
    }
  },
  "2024-11-20|Approval of Addendum to the 2024-25 Measure U Application for Adelante Selby Spanish Immersion": {
    "adelante-selby": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2024-11-20|Approval of Addendum to the 2024-25 Measure U Application for Taft Community School": {
    "taft": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2024-11-06|Approval of Contracts with QKA Architects for Design Services for the Following Projects Adelante Selby, Hoover School, Roosevelt School, and Taft School HVAC Upgrades Projects": {
    "adelante-selby": {
      "en": "Board design services contract for HVAC upgrades.",
      "es": "La junta aprobó el contrato de diseño para mejoras de HVAC."
    },
    "hoover": {
      "en": "Board design services contract for HVAC upgrades.",
      "es": "La junta aprobó el contrato de diseño para mejoras de HVAC."
    },
    "roosevelt": {
      "en": "Board design services contract for HVAC upgrades.",
      "es": "La junta aprobó el contrato de diseño para mejoras de HVAC."
    },
    "taft": {
      "en": "Board design services contract for HVAC upgrades.",
      "es": "La junta aprobó el contrato de diseño para mejoras de HVAC."
    }
  },
  "2024-09-25|Approval of Addendum to Garfield Community School's 2024-25 Measure U Application": {
    "garfield": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2024-08-07|Approval of Disbursement of Measure U Funds for the 2024-2025 School Year for Hoover Community School": {
    "hoover": {
      "en": "Board release of Measure U funds for 2024-25.",
      "es": "La junta aprobó la liberación de fondos de Measure U para 2024-25."
    }
  },
  "2024-06-26|Approval of Disbursement of Measure U Funds for the 2024-2025 School Year for Taft Community School": {
    "taft": {
      "en": "Board release of Measure U funds for 2024-25.",
      "es": "La junta aprobó la liberación de fondos de Measure U para 2024-25."
    }
  },
  "2024-06-05|Approval of Title I School-Wide Program for Clifford School": {
    "clifford": {
      "en": "Board Title I school-wide program designation.",
      "es": "La junta aprobó la designación del programa escolar Title I."
    }
  },
  "2024-05-22|Approval of Installation of Theatrical Lighting Fixtures LED with Musson at McKinley Institute of Technology": {
    "mckinley-mit": {
      "en": "Board installation of LED theatrical lighting.",
      "es": "La junta aprobó la instalación de iluminación teatral LED."
    }
  },
  "2024-05-10|CONFERENCE WITH REAL PROPERTY NEGOTIATORS Properties: Redwood City properties at 3150 Granger Way; 907 Roosevelt Avenue; 815 Allerton Street; 225 Clifford Avenue; 3790 Red Oak Way; 2223 Vera Avenue; 555 Ave del Oro; 2498 Massachusetts Avenue; 400 Duane Street Agency Negotiator: Rick Edson Negotiating Parties: Various tenants located at listed properties Under negotiation: price, terms of payment": {
    "clifford": {
      "en": "Board held closed session on district property lease negotiations.",
      "es": "La junta celebró sesión cerrada sobre negociaciones de arrendamiento de propiedades del distrito."
    }
  },
  "2024-05-08|Approval of the Addendum No. 2 to Orion's 2023-24 Measure U Application": {
    "orion": {
      "en": "Board second update to Measure U spending plan.",
      "es": "La junta aprobó la segunda actualización del plan de gastos de Measure U."
    }
  },
  "2024-05-08|Approval of the Addendum to North Star Academy's 2023-24 Measure U Application": {
    "north-star": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2024-04-17|Approval of the Addendum to McKinley Institute of Technology (MIT) 2023-24 Measure U Application": {
    "mckinley-mit": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2024-04-17|Approval of the Addendum to Taft's 2023-24 Measure U Application": {
    "taft": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2024-04-17|Approval of the Addendum to Clifford's 2023-24 Measure U Application": {
    "clifford": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  },
  "2024-04-03|Approval of Addendum to 2023-24 Measure U Application for Roy Cloud School": {
    "roy-cloud": {
      "en": "Board updated Measure U spending plan.",
      "es": "La junta aprobó el plan de gastos actualizado de Measure U."
    }
  }
}